Project Duration
Stipulated Date of Commencement October 28 2014
Actual Date of Completion May 09 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 45,817,308.00
Awarded for ₹ 49,506,270.40

Project highlights

Conversion of electrical overhead lines to underground cables.

 
Gallery Image
Contractors
M/s. Nanu Engineers Pvt. Ltd.,
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Bridge connecting Veluz and Dhabos in Valpoi including approaches.

View Details
Similar Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji

View Details
Similar Project

Construction of Poriem Bridge including approaches.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.