Project Duration
Stipulated Date of Commencement July 07 2016
Actual Date of Completion September 30 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 29,070,479.00
Awarded for ₹ 28,774,977.40

Project highlights

The work includes construction of foothpath from DTE along the Vidhya Prabodini along with electrfication .

 
Gallery Image
Contractors
M/s.Michael & Michael
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Providing and applying high build, crack building, electromeric, protective and waterproof coating to the Grade separator (2 flyovers) at Dabolim airport.

View Details
Similar Project

Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Panjim – HT Cable work from EDC Substation to Chimbel junction – Additional Work

View Details
Similar Project

Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Porvorim

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.