Project Duration
Stipulated Date of Commencement March 09 2014
Actual Date of Completion October 31 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 36,323,930.00
Awarded for ₹ 34,920,750.00

Project highlights

Construction of footpath from Sai Service Junction to Training College Junction at Porvorim.

 
Gallery Image
Contractors
M/s. Michael & Michael Constructions
Gallery Image
Consultants
M/s. Nitin P. Arolkar
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Construction of footpath from Sai Service junction to training college junction at Porvorim – Electrical works

100% Completed
 
Project Duration
Stipulated Date of Commencement February 27 2014
Actual Date of Completion July 15 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,232,612.00
Awarded for ₹ 9,932,510.00

Project highlights

The scope of work involves supply and installation of decorative street light poles on the Service road.

 
Contractors
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
Consultants
M/s. Nitin Arolkar
Similar Projects

See Similar Projects

Similar Project

Construction of Bridge for local farmers to cross river stream for cultivation of fields from Chune – Kator to Vanso Field in Village of Cumbarjua.

View Details
Similar Project

Construction of bridge across river between Aldona and Calvim.

View Details
Similar Project

Acoustic work for Multipurpose Hall.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.