Project Duration
Stipulated Date of Commencement February 22 2014
Actual Date of Completion November 30 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,889,214.00
Awarded for ₹ 12,222,932.73

Project highlights

The work includes construction of road from NH-4A to Miraculous Cross Church. Length of Road -700m, 25mm thick Asphalt Concrte ,50mm thick DBM ,50mm thicj BM along with Crash Barrier .

 
Gallery Image
Contractors
M/s.Ritesh Developers
Gallery Image
Consultants
M/s.Kashec Engineers Pvt Ltd .
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bus Stand at Honda.

View Details
Similar Project

Construction of footpath from Sai Service Junction to Training College Junction at Porvorim.

View Details
Similar Project

Dismantling of HT overhead lines, supplying & laying of HT underground cables at Panaji – Cable work from EDC substation to Chimbel junction.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.