Project Duration
Stipulated Date of Commencement
February 22 2014
Actual Date of Completion
July 04 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 42,752,453.00
Awarded for
₹ 44,016,624.00
Project highlights
Internal Roads of total approximate length of 3.8km hotmixed and widened at certain locations. Widening of Tolleaband road done
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates