Project Duration
Stipulated Date of Commencement February 22 2014
Actual Date of Completion July 04 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 42,752,453.00
Awarded for ₹ 44,016,624.00

Project highlights

Internal Roads of total approximate length of 3.8km hotmixed and widened at certain locations. Widening of Tolleaband road done

 
Gallery Image
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Upgradation and improvement of roads leading to beaches in Pernem Phase–I Chopdem to Mandrem.

View Details
Similar Project

Additional works from Sai Service Junction to Training College Junction at Porvorim, Goa

View Details
Similar Project

Hot mixing and Improvement of Internal Roads in V. P. Dramapur, Sirlim in Velim Constituency.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.