Project Duration
Stipulated Date of Commencement
February 27 2014
Actual Date of Completion
October 31 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 608,776,106.00
Awarded for
₹ 725,992,929.50
Project highlights
Project consists of construction of concrete road, cycle track, walkway, landscaping for the stretches from Miramar Circle to NIO Circle and from NIO Circle to Dona Paula Jetty and Raj Bhavan of total length of 4.4km
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. LKS India Pvt. Ltd.