Project Duration
Stipulated Date of Commencement May 26 2006
Actual Date of Completion January 30 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 36,482,879.00
Awarded for ₹ 44,187,674.21

Project highlights

Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, construction of culverts, providing gutters and cross drainages wherever required. The approximate length of the road is around 5.72 kms.

 
Gallery Image
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of footpath from Sai Service Junction to Training College Junction at Porvorim.

View Details
Similar Project

Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) :-Civil works.

View Details
Similar Project

Additional works from Sai Service Junction to Training College Junction at Porvorim, Goa

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.