Project Duration
Stipulated Date of Commencement
August 02 2003
Actual Date of Completion
June 30 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 42,004,000.00
Awarded for
₹ 39,063,000.00
Project highlights
The work involved improving the riding quality by providing bituminous layer.
Contractors
M/s. Sudin N. Verenker
Consultants
M/s. S. N. Bhobe & Associates Pvt. Ltd