Project Duration
Stipulated Date of Commencement
February 26 2014
Actual Date of Completion
December 21 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,20,38,902.00
Awarded for
₹ 88,735,464.00
Project highlights
Jetty length of 104 meters constructed to provide facility for Barges, launches, Cruise Operators industry. Designed according to Holistic Design of Panaji like glass railing, Olivio Grande LED fitting . Euipped with cathodic prevention system.
Contractors
M/s. Kargwal Constructions Pvt. Ltd.,
Consultants
M/s. Madhav Kamat & Associates, J