Project Duration
Stipulated Date of Commencement February 01 2019
Actual Date of Completion October 31 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 46,281,281.00
Awarded for ₹ 43,882,672.75

Project highlights

Retaining walls,pilling work, embakment, roads,electrical works etc.

 
Gallery Image
Contractors
M/s. Race Constructions
Gallery Image
Consultants
M/s. Keni D’Souza
 
Similar Projects

See Similar Projects

Similar Project

Upgradation and improvement of roads leading to beaches in Pernem Phase–I Chopdem to Mandrem.

View Details
Similar Project

Design & Construction of Bridge of Cumbarjua, Goa on RCC Bored Pile Foundaton.

View Details
Similar Project

Widening of roads and relocation of structures in Fatorda Constituency- Phase II

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.