Project Duration
Stipulated Date of Commencement
March 05 2014
Actual Date of Completion
August 31 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,506,358.95
Awarded for
₹ 32,467,272.50
Project highlights
Maintenance of bridges (North Goa)
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.,
Consultants
Pre tender – M/s. Kashec Engineers Pvt. Ltd.,
Post tender – In-house (GSIDC)
Sub Works
This project involved 1 sub works. The details of the same available below
1
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) -Electrical work
100% Completed
Project Duration
Stipulated Date of Commencement
March 05 2014
Actual Date of Completion
August 31 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 25,219,798.80
Awarded for
₹ 26,356,358.00
Project highlights
Maintenance of bridges
Contractors
M/s.Goa Friends Engineering & Electrical Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Improvement and Upgradation of the existing MDR from Dandevaddo to Chandor via Sarzora and Guddi in Cuncolim Constituency.
View Details
Construction of Bus Stand at Shiroda – Phase II : Civil works, internal electrification and road
View Details
Pedestrian Bridge Linking Central Library & Creek – Dynan Setu
View Details





