Project Duration
Stipulated Date of Commencement March 05 2014
Actual Date of Completion August 31 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 29,506,358.95
Awarded for ₹ 32,467,272.50

Project highlights

Maintenance of bridges (North Goa)

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.,
Gallery Image
Consultants
Pre tender – M/s. Kashec Engineers Pvt. Ltd., Post tender – In-house (GSIDC)
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) -Electrical work

100% Completed
 
Project Duration
Stipulated Date of Commencement March 05 2014
Actual Date of Completion August 31 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 25,219,798.80
Awarded for ₹ 26,356,358.00

Project highlights

Maintenance of bridges

 
Contractors
Contractors
M/s.Goa Friends Engineering & Electrical Pvt. Ltd.
Consultants
Consultants
In-house (GSIDC)
Similar Projects

See Similar Projects

Similar Project

Improvement and Upgradation of the existing MDR from Dandevaddo to Chandor via Sarzora and Guddi in Cuncolim Constituency.

View Details
Similar Project

Construction of Bus Stand at Shiroda – Phase II : Civil works, internal electrification and road

View Details
Similar Project

Pedestrian Bridge Linking Central Library & Creek – Dynan Setu

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.