Project Duration
Stipulated Date of Commencement
January 19 2014
Actual Date of Completion
January 25 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 334,479,486.00
Awarded for
₹ 277,200,000.00
Project highlights
The project consists of two lane composite steel girder bridge of 220 m length along with approaches of 1600 m on Amona side and 500 m on Virdi side. The bridge lighting is of signature high quality LED fittings.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Design and construction of Bridge across River Zuari between Amona and Virdi. SH: Supply of LED Fittings, Poles and Brackets
100% Completed
Project Duration
Stipulated Date of Commencement
February 26 2018
Actual Date of Completion
May 07 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,399,120.00
Awarded for
₹ 2,820,440.00
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Demolition of Old existing jetty and Reconstruction of New Captain of Ports jetty at Old Goa.
View Details
Construction over bridge at Valvanti river connecting Bhandarwada to Vithalapur Sankhali.
View Details
Hotmixing of Road from Sai Service Junction to Training College Junction at Porvorim, Goa
View Details