Project Duration
Stipulated Date of Commencement
August 08 2018
Actual Date of Completion
March 17 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,884,443.00
Awarded for
₹ 8,233,439.80
Project highlights
Site Development work
Contractors
M/s.Race Constructions
Consultants
M/s.UCJ Architecture & Environment
See Similar Projects
Development & Beautification of open spaces into Gardens at Nina Pinto Colony, Caculo Colony & Albamar Colony in Ward No.9 and 10 of Corporation of the City of Panaji.