Project Duration
Stipulated Date of Commencement January 16 2014
Actual Date of Completion December 31 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 181,834,018.64
Awarded for ₹ 177,480,773.00

Project highlights

The project includes Construction of Bus stand , Market and Community hall with adquate facility at Marcel Goa

 
Gallery Image
Contractors
M/s. Harsh Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Rahul Deshpande & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bus Stand & Mini Depot at Sankhali, Goa – Erection of 11KV line from Electricity Department feeder to bus stand substation.

View Details
Similar Project

Upgradation and improvement of roads leading to beaches in Pernem Phase–I Chopdem to Mandrem.

View Details
Similar Project

Dismantling of HT overhead lines, supplying & laying of HT underground cables at Panaji – Cable work from Kadamba substation to Chimbel junction.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.