Project Duration
Stipulated Date of Commencement
November 30 2023
Stipulated Date of Completion /
Likely Date of Completion February 28 2025
Likely Date of Completion February 28 2025
Status
35%
Completed
Cost (₹)
Estimated at
₹ 168,068,602.00
Awarded for
₹ 159,232,583.60
Project highlights
Auction Platform, Parking Bays, Finishing work, road work , ice flaking machine, cold storage, parking bays, FDA Testing, Office For traders, Cafeteria, Utility services & Drainage.
Contractors
M/s. R.Z. Malpani
Consultants
M/s. UCJ Architecture & Environment