Project Duration
Stipulated Date of Commencement
June 24 2022
Stipulated Date of Completion /
Likely Date of Completion September 30 2024
Likely Date of Completion September 30 2024
Status
34.1%
Completed
Cost (₹)
Estimated at
₹ 256,977,576.16
Awarded for
₹ 263,203,536.94
Project highlights
New Hostel Block is proposed in IPHB Campus for Resident Doctors and New students to be inducted for the courses in IPHB
Contractors
M/s. S K Construction
Consultants
M/s. FP Project Management