Project Duration
Stipulated Date of Commencement
June 07 2024
Stipulated Date of Completion /
Likely Date of Completion August 06 2024
Likely Date of Completion August 06 2024
Status
10%
Completed
Cost (₹)
Estimated at
₹ 3,279,407.36
Awarded for
₹ 3,350,000.00
Project highlights
Panels required for additional HVAC requirements from the Court and Façade Lighting.
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.
Consultants
M/s. Shrikhande Consultants Ltd.