Project Duration
Stipulated Date of Commencement August 02 2021
Stipulated Date of Completion /
Likely Date of Completion
August 31 2024
Status
95%
Completed
Cost (₹)
Estimated at ₹ 2,444,709.00
Awarded for ₹ 2,163,530.00

Project highlights

The work consists of additional requirements, such as hooters, supression system, etc, as asked by the Directorate of Fire and Emergency Services.

 
Gallery Image
Contractors
M/s. Antifire Systems,
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Expansion and Upgradation of the infrastructure of Primary Health Centre, Sanguem

View Project
Similar Project

Construction of Rural Medical Dispensary at Rivona under Primary Helath Centre, Quepem.

View Project
Similar Project

Upgradation and re-furbishment of Primary Health Centre, Curtorim.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.