Project Duration
Stipulated Date of Commencement
November 09 2017
Stipulated Date of Completion /
Likely Date of Completion March 31 2024
Likely Date of Completion March 31 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 41,902,954.49
Awarded for
₹ 39,462,508.00
Project highlights
The work consists of Nurse Call system, telephone system, UPS, Building Management System, LAN, CCTV, etc.