Project Duration
Stipulated Date of Commencement
May 31 2016
Stipulated Date of Completion /
Likely Date of Completion June 30 2016
Likely Date of Completion June 30 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 745,000.00
Awarded for
₹ 818,000.00
Project highlights
Providing 2 bay & Scrub sink, PVC flooring and OT surgical lights
Contractors
M/s.Mediotiz Installation
Consultants
M/s. Datta Kare Associates