Project Duration
Stipulated Date of Commencement
February 10 2024
Stipulated Date of Completion /
Likely Date of Completion August 10 2024
Likely Date of Completion August 10 2024
Status
45%
Completed
Cost (₹)
Estimated at
₹ 41,676,594.00
Awarded for
₹ 34,885,269.00
Contractors
M/s. Aai Jee Interiors
Consultants
M/s. Pankaj Joshi Consultants
See Similar Projects
Providing interiors, electrifications and other amenities to the office premises of Commercial Tax Department situated at Mapusa.
View Project
Construction of Terminal Building for Captain of Ports at Panaji, Goa – Civil, Plumbing, Electrical and Fire Fighting works
View Project
Renovation of Building of Directorate of Higher Education at Porvorim-Goa – Balance – Civil, Plumbing and Fire Fighting work
View Project