Project Duration
Stipulated Date of Commencement
January 21 2019
Stipulated Date of Completion /
Likely Date of Completion October 30 2024
Likely Date of Completion October 30 2024
Status
79%
Completed
Cost (₹)
Estimated at
₹ 241,324,334.26
Awarded for
₹ 251,748,000.85
Project highlights
New administrative buidling for the Captain of ports
Contractors
M/s. Kargwal Constructions Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of Terminal Building for Captain of Ports at Panaji, Goa – HVAC Works
30% completed
Project Duration
Stipulated Date of Commencement
March 17 2024
Stipulated Date of Completion /
Likely Date of Completion September 16 2024
Likely Date of Completion September 16 2024
Status
30%
Completed
Cost (₹)
Estimated at
₹ 7,613,773.00
Awarded for
₹ 6,988,850.00
Project highlights
Providing AC for Terminal Building.
Contractors
M/s Shree Manguirish Air Conditioning Co.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
External Development Work for Multipurpose Community Hall for Department of Tribal Welfare at Harvalem Sankhali Goa
View Project
Additional Miscellaneous Work in New High Court Complex at Penha De Franca, Porvorim – Goa.
View Project
Renovation of Building of Directorate of Higher Education at Porvorim-Goa – Balance – Civil, Plumbing and Fire Fighting work
View Project