Project Duration
Stipulated Date of Commencement
February 15 2019
Stipulated Date of Completion /
Likely Date of Completion October 30 2024
Likely Date of Completion October 30 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 12,999,323.61
Awarded for
₹ 16,312,056.87
Project highlights
G+1 structure. Panchayat building with shops on ground floor and hall on first floor
Contractors
M/s. Vaishnavi Infra Developers Pvt. Ltd
Consultants
M/s Creative Abode
See Similar Projects
Reconstruction of Panchayat Ghar along with commercial shops, hall and other amenities for administrative purpose at Molcornem, Quepem, Goa.