Project Duration
Stipulated Date of Commencement
February 10 2023
Stipulated Date of Completion /
Likely Date of Completion August 17 2023
Likely Date of Completion August 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,637,094.00
Awarded for
₹ 1,699,807.30
Project highlights
Fire Fighting System works
Contractors
M/s.Fyreguard Enterprises
Consultants
M/s. Ameet Sukhthankar Architects & Interior Designers
See Similar Projects
HVAC work.
View Project
Construction of Office Building for Information Technology Department at Altinho, Panaji.
View Project
Supply, Installation, Testing & Commissioning of CCTV system at Goa Medical College.
View Project





