Project Duration
Stipulated Date of Commencement
November 01 2018
Stipulated Date of Completion /
Likely Date of Completion January 31 2019
Likely Date of Completion January 31 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,242,623.00
Awarded for
₹ 5,949,043.80
Project highlights
Construction of foundation for installtion of shinohara offset printing machine procured by the department. The premises of machine area is renovated and is equipped with HVAC as per machine requirment for dust free environment.
Contractors
M/s.Kamat Equipment Services
Consultants
M/s.Rajesh Kenkre