Project Duration
Stipulated Date of Commencement
June 30 2007
Stipulated Date of Completion /
Likely Date of Completion September 30 2008
Likely Date of Completion September 30 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 54,521,530.00
Awarded for
₹ 70,197,527.00
Project highlights
Restoration works
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.