Project Duration
Stipulated Date of Commencement
August 30 2004
Stipulated Date of Completion /
Likely Date of Completion December 26 2004
Likely Date of Completion December 26 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,938,000.00
Awarded for
₹ 20,933,000.00
Project highlights
1) Hard landscaping like compound wall, paved plazas, semi-paved decks, spaces, kerbs, parking areas, café sitouts, planter boxes, etc.
2) Soft landscaping like lawns, vases, trees, specimen plants, shrubs, rockery, pebbles and also includes services like stormwater drainage, external electrical works, landscape plumbing and street furniture.
Contractors
M/s. R. B. S. Candiaparcar
Consultants
M/s. Prabhugaonker & Associates
See Similar Projects
Construction of Multipurpose Hall and Office Building for Village Panchayat Salvador Do Mundo : Civil, Plumbing, Electrical & HVAC works
View Project
Construction of Multiplex.
View Project
Upgradation of infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 – Reconstruction of Panchayat building at V.P.Honda.
View Project