Project Duration
Stipulated Date of Commencement
January 12 2008
Stipulated Date of Completion /
Likely Date of Completion January 30 2008
Likely Date of Completion January 30 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 88,445.00
Awarded for
₹ 91,290.00
Project highlights
Providing rumbler strips and signboard
Contractors
M/s. Thermoline India
Consultants
In-house (GSIDC)