Project Duration
Stipulated Date of Commencement
July 31 2015
Stipulated Date of Completion /
Likely Date of Completion September 30 2015
Likely Date of Completion September 30 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,627,884.00
Awarded for
₹ 5,477,777.00
Project highlights
Interior work for TCP branch office
Contractors
M/s. Harshada Trading co.
Consultants
M/s. Intrinsic Classic