Project Duration
Stipulated Date of Commencement
April 13 2016
Stipulated Date of Completion /
Likely Date of Completion February 05 2016
Likely Date of Completion February 05 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,125,160.00
Awarded for
₹ 3,377,777.00
Project highlights
Civil, plumbing and dismantling work for office of STPI, Goa.
Contractors
M/s. Harshada Trading co.
Consultants
M/s. Pankaj Joshi Consultants