Project Duration
Stipulated Date of Commencement
February 27 2009
Stipulated Date of Completion /
Likely Date of Completion August 26 2009
Likely Date of Completion August 26 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,541,225.00
Awarded for
₹ 10,902,411.00
Project highlights
Construction of retaining wall, compound wall and land filling etc.
Contractors
M/s. Rohit Equipments
Consultants
M/s. Banaji & Associates