Project Duration
Stipulated Date of Commencement August 20 2014
Stipulated Date of Completion /
Likely Date of Completion
November 19 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 60,002,811.80
Awarded for ₹ 54,000,000.00

Project highlights

Temporary office premises for GSIDC office and the District & Sessions Court untill the permanent premises is ready to be occupied.

 
Gallery Image
Contractors
M/s. Knchan Associates,
Gallery Image
Consultants
M/s. Ameet Sukhthankar Architect,
 
Similar Projects

See Similar Projects

Similar Project

Construction of Fire Station at Curchorem-Box Culvert Work.

View Project
Similar Project

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa

View Project
Similar Project

Civil, Plumbing & internal electrical works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.