Project Duration
Stipulated Date of Commencement
January 03 2006
Stipulated Date of Completion /
Likely Date of Completion February 02 2006
Likely Date of Completion February 02 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 64,000.00
Awarded for
₹ 65,000.00
Contractors
M/s. Home Deco
Consultants
M/s. Rahul Deshpande & Associates