Project Duration
Stipulated Date of Commencement
December 20 2012
Stipulated Date of Completion /
Likely Date of Completion March 19 2013
Likely Date of Completion March 19 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,979,866.00
Awarded for
₹ 16,540,030.00
Project highlights
Providing of furniture for Office, Canteen, Auditorium, Guest room, Green rooms etc.

Contractors
M/s. Concept Creators

Consultants
M/s. Consulting Engineering Services Pvt. Ltd.