Project Duration
Stipulated Date of Commencement
January 12 2014
Stipulated Date of Completion /
Likely Date of Completion February 28 2015
Likely Date of Completion February 28 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,223,672.00
Awarded for
₹ 3,374,000.00
Contractors
M/s. GMP Technical Solutions Pvt. Ltd
Consultants
M/s. Effective Architectural Services