Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion May 25 2014
Likely Date of Completion May 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,096,751.00
Awarded for
₹ 31,460,654.00
Contractors
M/s.Hi Tech Audio Systems Pvt Ltd
Consultants
M/s. Effective Architectural Services