Project Duration
Stipulated Date of Commencement
July 09 2012
Stipulated Date of Completion /
Likely Date of Completion June 12 2012
Likely Date of Completion June 12 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,28,94,732.00
Awarded for
₹ 37,798,417.00
Project highlights
Readymade Furniture works
Contractors
M/s. Durian Industries Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
See Similar Projects
Signages work
View Project
False ceiling work.
View Project
Construction of Building for Science Faculty at Goa University, Taleigao, Tiswadi Goa – Civil, electrification & land development work.
View Project





