Project Duration
Stipulated Date of Commencement
October 25 2013
Stipulated Date of Completion /
Likely Date of Completion November 14 2013
Likely Date of Completion November 14 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 384,228.00
Awarded for
₹ 390,000.00
Project highlights
The scope of work involved servicing of 750kVA DG set and 750kVA Transformer.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
UCJ architecture & environment
See Similar Projects
Interior Works for Office Premises for Departments / Corporations at EDC, Patto Plaza, Panaji, Goa
View Project
Repairs and Upgradation of solid waste management facilities within the jurisdiction of CCP in Panjim City – Civil Works
View Project
Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators for various projects in Goa.
View Project





