Project Duration
Stipulated Date of Commencement April 22 2012
Stipulated Date of Completion /
Likely Date of Completion
May 07 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 87,89,272.80
Awarded for ₹ 8,250,144.00

Project highlights

Decorative Glazing works

 
Gallery Image
Contractors
M/s. R. S. Lawande
Gallery Image
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

External painting of buildings for IFFI 2014.

View Project
Similar Project

CCTV work.

View Project
Similar Project

Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim-Goa – Interior & Furniture works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.