Project Duration
Stipulated Date of Commencement
December 14 2018
Stipulated Date of Completion /
Likely Date of Completion April 13 2019
Likely Date of Completion April 13 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1.10 cr
Awarded for
₹ 0.89 cr
Project highlights
Interior Works for FDA block at Margao
Contractors
M/s. Creation Interior Contractors
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD