Project Duration
Stipulated Date of Commencement
June 16 2009
Stipulated Date of Completion /
Likely Date of Completion November 15 2009
Likely Date of Completion November 15 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,783,602.00
Awarded for
₹ 7,994,225.00
Contractors
M/s. Hindustan Construction Corporation
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.