Project Duration
Stipulated Date of Commencement
September 04 2009
Stipulated Date of Completion /
Likely Date of Completion March 03 2010
Likely Date of Completion March 03 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,013,381.00
Awarded for
₹ 19,163,609.00
Project highlights
AC work for the project
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.