Project Duration
Stipulated Date of Commencement
December 11 2014
Stipulated Date of Completion /
Likely Date of Completion February 10 2015
Likely Date of Completion February 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,582,490.00
Awarded for
₹ 4,199,999.00
Project highlights
Additional AC works required for completion of project
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works for the stretch from NIO Circle to Miramar circle, NIO circle to Rajbhavan, NIO circle to Dona Paula Jetty & NIO circle to Odxel Junction
View Project
Supply, erection and commissioning of Diesel Generator Sets
View Project
Public works in Calangute Constituency.
View Project