Project Duration
Stipulated Date of Commencement
June 23 2008
Stipulated Date of Completion /
Likely Date of Completion March 23 2009
Likely Date of Completion March 23 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,610,674.00
Awarded for
₹ 15,968,204.24
Project highlights
Renovation of existing garden with construcion of service duct, footpath, parapet wall, landscaping, benches and elecrical poles.
Contractors
M/s. K. G. Thomas
Consultants
M/s Effective Architectural Services
( Honorary)