Project Duration
Stipulated Date of Commencement June 12 2012
Stipulated Date of Completion /
Likely Date of Completion
May 02 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,839,786.00
Awarded for ₹ 6,220,033.00

Project highlights

Providing of structural work like catwalk, in the building

 
Gallery Image
Contractors
M/s. T. S. Mistry
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Fish & Vegetable Market Complex at Sanquelim.

View Project
Similar Project

Balance beautification works from Miramar Circle to Betim Ferry Ramp

View Project
Similar Project

Construction of Footpath at Old Goa for Exposition 2014

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.