Project Duration
Stipulated Date of Commencement
June 12 2012
Stipulated Date of Completion /
Likely Date of Completion May 02 2013
Likely Date of Completion May 02 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,839,786.00
Awarded for
₹ 6,220,033.00
Project highlights
Providing of structural work like catwalk, in the building
Contractors
M/s. T. S. Mistry
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Construction of Market complex cum Community Hall in Chodan-Madel Village Panchayat
View Project
Signages.
View Project
Construction of Shri. Manohar Parrikars Smriti Sthal at Miramar
View Project





