Project Duration
Stipulated Date of Commencement April 26 2011
Stipulated Date of Completion /
Likely Date of Completion
October 25 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,373,990.00
Awarded for ₹ 12,323,666.60

Project highlights

Fire fighting works for Ravidra Bhavan

 
Gallery Image
Contractors
M/s. Fire Remedy Systems
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Landscaping work in the state of Goa

View Project
Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Pernem Taluka : Construction of Panchayat Complex cum Multipurpose Hall at V. P. Querim – Tiracol

View Project
Similar Project

Upgradation of facilities of Pilgrims for Exposition 2014 at Old Goa – Internal works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.