Project Duration
Stipulated Date of Commencement
September 13 2013
Stipulated Date of Completion /
Likely Date of Completion September 27 2013
Likely Date of Completion September 27 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 461,294.00
Awarded for
₹ 461,294.00
Project highlights
Refurbishment work of Maquiniz Palace complex prior to IFFI 2013.
Contractors
M/s. Pest Control (India) Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment
See Similar Projects
Interior work for TCP branch office, Tiswadi Branch, 5th Floor, Kamat Towers
View Project
Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim- Goa. Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works
View Project
Repairs and Upgradation of solid waste management facilities within the jurisdiction of CCP in Panjim City – Civil Works
View Project