Project Duration
Stipulated Date of Commencement
September 13 2013
Stipulated Date of Completion /
Likely Date of Completion September 27 2013
Likely Date of Completion September 27 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 461,294.00
Awarded for
₹ 461,294.00
Project highlights
Refurbishment work of Maquiniz Palace complex prior to IFFI 2013.
Contractors
M/s. Pest Control (India) Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment