Project Duration
Stipulated Date of Commencement
September 13 2013
Stipulated Date of Completion /
Likely Date of Completion September 27 2013
Likely Date of Completion September 27 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 461,294.00
Awarded for
₹ 461,294.00
Project highlights
Refurbishment work of Maquiniz Palace complex prior to IFFI 2013.
Contractors
M/s. Pest Control (India) Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment
See Similar Projects
Internal, external and special lighting fixtures (Part B : External lights and façade lighting)
View Project
Erection, testing and commissioning of Air Conditioned Hanger at Dayanad Bandodkar Football Ground, Campal, Panaji, Goa for IFFI 2012.
View Project
Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim- Goa. Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works