Project Duration
Stipulated Date of Commencement
October 29 2007
Stipulated Date of Completion /
Likely Date of Completion November 12 2007
Likely Date of Completion November 12 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 903,000.00
Awarded for
₹ 584,000.00
Contractors
M/s. Coral Telecom Ltd.
Consultants
M/s. Effective Architectural Services