Project Duration
Stipulated Date of Commencement November 14 2017
Stipulated Date of Completion /
Likely Date of Completion
December 14 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,019,832.00
Awarded for ₹ 8,371,107.76

Project highlights

Painting of buildings for IFFI 2017

 
Gallery Image
Contractors
M/s.Rakesh Kambli
Gallery Image
Consultants
M/s.Vaishali Pednekar & Associates
 
Similar Projects

See Similar Projects

Similar Project

Panaji to Pollem (Part III) – Chainage 62.60 km. to 93.90 km.

View Project
Similar Project

Construction of High Court Complex at Penha de Franca, Porvorim.

View Project
Similar Project

Supply of hydraulic wrecker crane with under lift capacity of 2.5 tons.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.