Project Duration
Stipulated Date of Commencement October 22 2012
Stipulated Date of Completion /
Likely Date of Completion
November 20 2012
Status

Completed
Cost (₹)
Estimated at ₹ 19,999,329.00
Awarded for ₹ 21,373,046.70

Project highlights

Repair and minor civil works of Kala Academy building in view of IFI 2012.

 
Gallery Image
Contractors
M/s. H. Candolkar & Sons
Gallery Image
Consultants
M/s. Nilesh Salkar Associates
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing & commissioning of audio visual equipments and video conferencing system.

View Project
Similar Project

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa -Civil, Plumbing, Internal Electrical & Fire Fighting works

View Project
Similar Project

Fire suppression system.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.