Project Duration
Stipulated Date of Commencement
October 22 2012
Stipulated Date of Completion /
Likely Date of Completion November 20 2012
Likely Date of Completion November 20 2012
Status
Completed
Cost (₹)
Estimated at
₹ 19,999,329.00
Awarded for
₹ 21,373,046.70
Project highlights
Repair and minor civil works of Kala Academy building in view of IFI 2012.
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Nilesh Salkar Associates